Mohan Villa - Ernakulam
ApprovedMaterial Cost₹32.00 L
Labor Cost₹18.00 L
Contingency₹5.00 L
Total Cost₹55.00 L
Budget: ₹65.00 L | Variance: ₹10.00 L
Babu Apartment - Palakkad
SharedMaterial Cost₹21.00 L
Labor Cost₹12.00 L
Contingency₹3.00 L
Total Cost₹36.00 L
Budget: ₹42.00 L | Variance: ₹6.00 L
Rajan Luxury Villa - Kozhikode
DraftMaterial Cost₹50.00 L
Labor Cost₹28.00 L
Contingency₹8.00 L
Total Cost₹86.00 L
Budget: ₹95.00 L | Variance: ₹9.00 L
Material Cost Sample — Mohan Villa, Ernakulam
| Material Item | Quantity | Unit | Rate (₹) | Total (₹) | |
|---|---|---|---|---|---|
| Cement (UltraTech 53 Grade) | 200 | Bags | 450 | 90,000 | |
| Steel TMT Bars (Fe500) | 5 | Tons | 85,000 | 425,000 | |
| Bricks (Red) | 10000 | Nos | 8 | 80,000 | |
| M-Sand | 50 | Loads | 1,200 | 60,000 | |
| Concrete Blocks | 2000 | Nos | 45 | 90,000 | |
| Sub Total | ₹745,000 |